Portfolio snapshot for the PMO. Figures update as project records change.
Strategic Alignment
6 of 6 active projects are linked to a strategic objective.
- Objectives
- 5
- Linked active projects
- 6
Portfolio Health
Needs Attention3On trackAviation Academy Digital Learning, Regulatory Licensing Portal, Smart Airport Operations Centre
3Needs attentionAirspace Modernisation Programme, Drone Registration Platform, Airport Safety Audit Programme
3At riskATC Systems Upgrade, Aeronautical Information Management System, Accident Investigation Case System
1On holdRemote Tower Feasibility Study
- 2 projects are behind schedule (SPI below 0.90).
- 1 project has spent more than its budget.
- 1 critical issues and 3 high risks are open.
Based on overdue projects, critical issues and high risks.
Risk Heatmap
Open Risks & IssuesOpen risks by probability and impact.
111312111
Total Projects10Including 1 in initiation
Active Projects6Planning, execution and monitoring
Completed2In the closing stage
On Hold / Cancelled1Paused or stopped
Open Risks123 high or criticalOpen Issues51 criticalTotal BudgetAED 357.0MApproved, all projects
Actual CostAED 224.5M63% of budget spent1 project over its budget
Contract Value / Total PaidAED 346.7MAED 206.7M paid (60%)
Average SPI0.95Below 1.00 means behind schedule
Average CPI1.00Below 1.00 means over cost
Stakeholders20Recorded across all projectsProjects at Risk
All projectsRanked by the lower of SPI and CPI.
- 1ATC Systems UpgradeSPI 0.84 · CPI 0.890.84
- 2Accident Investigation Case SystemSPI 0.95 · CPI 0.860.86
- 3Aeronautical Information Management SystemSPI 0.88 · CPI 0.870.87
- 4Airport Safety Audit ProgrammeSPI 0.91 · CPI 1.030.91
- 5Airspace Modernisation ProgrammeSPI 0.95 · CPI 0.930.93
Budget vs Actual
Cumulative cost this year against planned spend.
Planned spendActual cost
- Total Budget
- AED 357.0M
- Planned spend
- AED 211.0M
- Actual cost
- AED 224.5M
Actual cost is 6% above planned spend to date.
Delivery Predictability
- On schedule5
- Slipping (0.90 to 0.95)2
- Late (below 0.90)2
Share of live projects with SPI of 0.95 or more.
Projects by Status
Projects by Priority
2Critical
4High
3Medium
1Low
Progress, Milestones and Tasks
- 52%Average progress
- 50%Milestones25 of 508 overdue
- 30%Tasks6 of 207 overdue
Projects by Sector
Recent Projects
All projects| Project | Status | Progress | SPI | CPI | Health |
|---|---|---|---|---|---|
| Smart Airport Operations Centre | Initiation | 1.00 | 1.33 | On track | |
| Remote Tower Feasibility Study | On Hold | 0.50 | 1.00 | On hold | |
| Regulatory Licensing Portal | Closing | 1.00 | 1.06 | On track | |
| Accident Investigation Case System | Closing | 0.95 | 0.86 | At risk | |
| Aeronautical Information Management System | Planning | 0.88 | 0.87 | At risk | |
| Aviation Academy Digital Learning | Execution | 1.06 | 1.11 | On track |
Top Strategic Objectives
All objectives- Digitise regulatory services53%6 projects
- Strengthen aviation safety65%5 projects
- Modernise airspace and air navigation44%4 projects
- Improve efficiency and sustainability10%2 projects